Tuesday, October 28, 2014

Windows

All of the six windows have been installed.


Surprisingly the installation went according to plan with just a couple of minor deviations.


The frames were built and installed in the building last year and had to wait a long time to receive their windows.


About ten days from now lime plaster will be applied to the exterior, weather permitting.


Then a door needs to be built and all the remaining will be done inside.


And this is what the building looked like on this day last year.